Abu Dhabi has introduced new construction rules covering new and ongoing building projects, updating how certain construction stages are documented and approved while clarifying the responsibilities of contractors and supervision consultants.
The Urban Planning and Permits Centre (UPPC), under the Department of Municipalities and Transport (DMT), issued Circular No. 9 of 2026 on October 14, 2026. According to the Emirates News Agency (WAM), the circular aims to streamline construction procedures, clarify professional responsibilities and maintain quality and safety standards across the emirate.
One of the main changes is the acceptance of certified technical reports instead of traditional phase-closure permits for designated project categories. However, mandatory site inspections and required approvals from other authorities remain in place where applicable.
Here's what the new construction rules cover and what developers and property buyers should understand about the changes.
What Are Abu Dhabi's New Construction Rules?
Circular No. 9 of 2026 regulates the roles and responsibilities of supervision consultants and contractors throughout construction.
The requirements apply to new and ongoing building projects in Abu Dhabi. They cover structural, architectural, mechanical, electrical and plumbing (MEP) works, along with other construction activities or phases identified by the relevant building control authority.
The main changes concern three areas:
- Construction documentation: Contractors must systematically document work throughout the construction process.
- Technical reporting: Completed construction phases must be documented in certified technical reports, including details of the work carried out, inspection results and any corrective actions.
- Professional accountability: Contractors and supervision consultants have defined responsibilities and share liability for non-compliant or defective work within their respective legal responsibilities.
These measures update the documentation and approval process while retaining the applicable construction oversight requirements.
How Does the New Abu Dhabi Construction Approval Process Work?
Under the circular, certified technical reports submitted through the Unified Permitting System can replace traditional phase-closure permits for designated project categories.
The process requires contractors and supervision consultants to document construction activities and provide records of completed work.
1. Notify the Supervision Consultant Before Major Construction Phases
Before starting a major construction phase, contractors must formally notify the supervision consultant and document site conditions according to the approved procedures.
This creates a record of the work and site conditions at the relevant stage of construction.
2. Prepare a Certified Technical Report
When a construction phase is completed, a technical report must be prepared, dated and signed by both the contractor and supervision consultant.
The report must describe the work carried out, inspection results and any corrective actions taken. Photographic evidence and visual technical reports are also required as part of the strengthened documentation process.
3. Submit the Report Through the Unified Permitting System
The supervision consultant is responsible for submitting the report through Abu Dhabi's Unified Permitting System.
For designated project categories, the UPPC accepts these certified reports in place of traditional phase-closure permits. The alternative process is intended to simplify the relevant administrative procedures.
However, the circular does not establish that every construction stage or project can use this alternative. Developers and construction professionals should consult the applicable requirements for their project category.
What Are the Responsibilities of Contractors and Supervision Consultants?
The circular clarifies the responsibilities of contractors and supervision consultants during construction and establishes joint liability for non-compliance, defects and work that does not meet required standards within their respective legal responsibilities.
Contractors must document construction work systematically, notify supervision consultants before major phases and provide the required records of completed work.
Supervision consultants must monitor construction activities against approved drawings, technical specifications and building codes. They are also responsible for submitting certified technical reports through the Unified Permitting System.
Both parties must meet their applicable obligations. The use of certified technical reports does not remove their statutory responsibilities.
Where violations are identified, the relevant authorities may take enforcement action, including fines and legal penalties under the applicable rules.